Work out each piece of the pour in cubic feet, add them, convert to cubic yards and add waste. Then decide between bags and a ready-mix truck, and have the details ready when you call the plant.

Concrete Order Worksheet

MeasureToBuy
Project / site address
Pour date

Volume

Item (slab, footing, steps…)Length (ft)Width (ft)Depth (ft)QtyCu ft (L × W × D × qty)

Order

Total cu ft
÷ 27 = cu yd
× (1 + waste, usually 5–10%)
Ready-mix order (round up to ¼ yd)
Or 80 lb bags (cu ft ÷ 0.60)
Or 60 lb bags (cu ft ÷ 0.45)

For the supplier

Mix / strength specified
Delivery time window
Truck access & distance to pour
Pump or chute needed?
Short-load / minimum fee
Supplier & phone

Formulas

Slab or footing  = length × width × thickness   (inches ÷ 12 = feet)
Cubic yards      = cubic feet ÷ 27
Bags             = cubic feet ÷ bag yield   (80 lb ≈ 0.60 cu ft, 60 lb ≈ 0.45, 40 lb ≈ 0.30)