How Deep Should a Paver Base Be? Base, Sand & Dig Depth

ICPI minimum base depths for paver patios, walks and driveways, the 1 in sand bed, how deep to dig, and a worked example with tons of gravel.

Updated October 18, 2026

The short answer

The Interlocking Concrete Pavement Institute (ICPI) gives a minimum compacted aggregate base of 4–6 in (100–150 mm) for walks and patios and 6–8 in (150–200 mm) for driveways. On top goes a 1 in (25 mm) screeded bed of coarse sand, then the pavers.

Dig depth = compacted base + 1 in sand + paver thickness

The layers under a paver

  • Compacted subgrade: the native soil, compacted so it doesn’t settle later.
  • Aggregate base: crushed stone with fines (crusher run, road base) compacted in layers. It carries the load and lets water drain.
  • Bedding sand: a 1 in screeded layer that the pavers are set into and vibrated down.
  • Pavers, with sand swept into the joints and an edge restraint holding the open sides.

Base depth by use

From ICPI Tech Spec 10, which notes that thicknesses may need to be greater depending on soil, freezing and traffic:

UseMinimum compacted basePaver thickness
Walks and patios4–6 in (100–150 mm)2⅜ in (60 mm)
Residential driveways6–8 in (150–200 mm)2⅜ in (60 mm)
Streets8–12 in (200–300 mm)3⅛ in (80 mm) or more

When to go deeper

Use the deeper end of each range, or more, when:

  • the soil is clay, silt or poorly drained;
  • the ground freezes in winter;
  • the patio will carry vehicles, a hot tub or other heavy loads;
  • you’re filling a low spot rather than digging into firm ground.

ICPI recommends review by a qualified design professional for difficult sites and anything carrying regular vehicle traffic.

How deep to dig

Add up the layers below the finished surface. With a 4 in base, 1 in of sand and 2⅜ in pavers you dig 7⅜ in below where the patio surface will be — measured from the finished height, which should slope gently away from the house so water runs off.

Worked example: a 12 × 12 ft patio

Area          12 × 12 = 144 sq ft
Base (4 in)   144 × 4 ÷ 12 = 48 cu ft × 1.15 compaction = 55.2 cu ft = 2.04 cu yd
              2.04 × 1.55 tons per cu yd ≈ 3.17 tons of crusher run
Sand (1 in)   144 × 1 ÷ 12 = 12 cu ft ≈ 1,200 lb
Dig depth     4 + 1 + 2⅜ = 7⅜ in

Compacting the base

ICPI notes that compacted lift thickness depends on the compaction equipment, typically 4–6 in per lift — check your plate compactor’s recommendation. Loose stone loses volume as it compacts, which is why we order about 15% more than the compacted volume.

Calculate it for your project

The Paver Calculator works out pavers, base tons, sand, polymeric sand, edging and dig depth together. Planning the whole job? Use the patio planner.