Skip to content
MeasureToBuy

Concrete Footing Calculator

Enter a continuous wall footing, a set of round pier footings, or both. You'll get the concrete volume, premix bags, a ready-mix order, and the rebar to buy for the continuous run.

Structural sizes — footings, framing, stairs — are governed by local building codes and site conditions. Use this for material planning, and confirm sizes with your building department or an engineer.

Measurements

Footing type

Strip footing under a wall

Total run, e.g. the perimeter of a foundation.

Commonly 12–24 in, about twice the wall thickness.

Thickness of the concrete, not the depth of the trench below grade.

Bars running the length of the footing. 2 × #4 is typical.

Waste allowance

Covers uneven ground, form bowing and spillage. 5–10% is standard.

Advanced optionscoverage, sizes, custom values

Bent bars tying the footing to the wall above. 0 to skip.

Bag size

0.60 cu ft per bag

Your estimate

You need about 1.45 cubic yards of concrete.

1.32 cu yd of footing, plus 10% waste.

Continuous footing40 ft × 16 in × 8 in
1.32 cu yd
Same volume
35.6 cu ft
Waste allowance
10%
Volume with waste
1.45 cu yd
80 lb premix bags0.6 cu ft per bag
66 bags
Or ready-mix orderrounded up to ¼ yard
1.5 cu yd
Approximate weight
5,860 lb

Rebar

Longitudinal bars40 ft each
2 bars
Length incl. 10% laps
88 ft
20 ft bars to buy
5 bars
  • Footings must bear on undisturbed soil below the local frost line. Frost depth and minimum sizes are set by your building department — check before you dig.
Continuous footing · section
GRADEFROST LINE · CHECK LOCAL CODE16 in8 in× 40 ft RUN2 BARS
Footing = length × 16 in × 8 in. The bottom must sit below your local frost line.

Next step

Build the wall on top

Count blocks, mortar and core fill for a block wall on this footing.

Concrete Block Calculator

Also useful

Truck or bags?

You need about 1.45 cu yd. Compare ready-mix delivery with bagged concrete at your prices.

Estimate concrete cost

How to measure

  1. Continuous footing: measure the total run along the centerline. For a rectangular foundation, that's roughly the perimeter.
  2. Footing width and depth are the concrete's cross-section — for example 16 in wide × 8 in thick — not how far the trench goes below grade.
  3. Piers: count the holes, then measure one hole's diameter (or the tube form size) and its depth from the top of the concrete to the bottom of the hole.
  4. Rebar: count the bars that run lengthwise in the footing (two #4 bars is common), and any vertical dowels that will tie into the wall above.
  5. Before digging, ask your building department for the frost depth and minimum footing size where you live.

How the concrete footing calculation works

Continuous footing = length × width × depth
Piers              = count × π × (diameter ÷ 2)² × depth
Order              = (footing + piers) × (1 + waste)

Longitudinal rebar = bars × length × 1.10 (lap splices)
Bars to buy        = ⌈rebar ÷ 20 ft⌉ + ⌈dowels ÷ dowels per bar⌉

A continuous footing is a long rectangular block, so its volume is length × width × depth. A pier is a cylinder: the area of its circle times its depth. The calculator converts every measurement to the same unit first, so you can mix feet and inches freely.

Bars in a footing overlap where they join. Adding 10% to the run covers those laps. Vertical dowels are cut from whole bars, and any leftover shorter than one dowel is counted as scrap.

Bag counts use the published premix yields (0.60 cu ft per 80 lb bag), and ready-mix rounds up to the next quarter yard.

Worked example

A 40 ft continuous footing, 16 in wide and 8 in thick, with two #4 bars and 10% extra.

  1. Width and depth in feet: 16 ÷ 12 = 1.333 ft; 8 ÷ 12 = 0.667 ft
  2. Volume: 40 × 1.333 × 0.667 = 35.6 cu ft (1.32 cu yd)
  3. With 10% waste: 35.6 × 1.1 = 39.1 cu ft (1.45 cu yd)
  4. 80 lb bags: 39.1 ÷ 0.6 = 65.2 → 66 bags; ready-mix: 1.5 cu yd
  5. Rebar: 2 × 40 ft = 80 ft × 1.1 = 88 ft ÷ 20 = 4.4 → 5 bars

Order 1.5 cubic yards of ready-mix (or 66 × 80 lb bags) and five 20 ft #4 bars. Six 12 in piers 4 ft deep would add another 18.9 cu ft.

How much extra to allow

Footing trenches are rarely as neat as the plan. Running short partway through a footing leaves a weak cold joint, so order generously.

SituationAllow
Formed footing on a clean, level base5%
Typical trench footing or tube forms10%
Hand-dug holes, sandy or caving soil15%

Reading your result

The highlighted row is how to buy the concrete: bags for small pier jobs, ready-mix once you're over about 1½ cubic yards.

The rebar total is for the continuous footing only. Piers usually get a vertical bar or a post anchor — add those separately.

If you're pouring footings and piers on the same day, choose 'Both' so the ready-mix order is rounded once.

Assumptions

  • Trench sides are straight and the bottom is level. Over-dug or crumbling trenches take more concrete — that's what the waste allowance is for.
  • Rebar laps add about 10% to each continuous run. Corner bends and chairs aren't counted separately.
  • Bars come in 20 ft lengths in the US and 6 m lengths in metric markets.
  • Concrete weighs about 150 lb per cubic foot (2,400 kg/m³).

Unit conversions use exact definitions (1 in = 25.4 mm, 1 US gal = 3.785 L). See the calculation methodology for rounding rules.

When to call a professional

  • Footing size, depth and reinforcement are structural decisions set by soil and code. Get them from your building department, plans or an engineer, and book any required inspection before you pour.
  • Foundations for living space, retaining walls and anything on expansive clay or a slope need an engineer or experienced contractor.

Frequently asked questions

How deep should a footing be?

The bottom must sit below your local frost line on undisturbed soil — anywhere from 12 in in warm climates to 48 in or more in the north. Your building department sets the number.

How wide should a footing be?

For light-frame houses, typical footings are 12–24 in wide and at least 6 in thick, often about twice the width of the wall on top. Heavier loads and weak soils need wider footings.

How many bags of concrete for a 12 in sonotube 4 ft deep?

One 12 in × 4 ft pier holds 3.14 cu ft. With 10% extra, that's about 3.5 cu ft, or six 80 lb bags.

Do footings need rebar?

Most codes require it for foundation footings — commonly two #4 bars running lengthwise. Small deck piers often use just a single vertical bar or none; check your local requirements.

More concrete & masonry calculators

All concrete & masonry