How to measure
- Measure length, width and thickness of the pour, or enter a volume you already know.
- Pick a mix ratio by volume: cement : sand : gravel. 1 : 2 : 3 is a good general-purpose mix.
- Check the bag weight. US Portland cement comes in 94 lb bags (1 cu ft); metric bags are usually 25 kg.
How the cement calculation works
Wet volume = length × width × thickness Dry volume = wet volume × (1 + waste) × 1.54 Cement = dry volume × 1 ÷ (sum of ratio parts) Sand, gravel = dry volume × their parts ÷ (sum of parts) Tons = cu yd × 1.35 (sand) or 1.4 (gravel) Water ≈ cement weight × 0.5
Loose cement, sand and gravel shrink by about a third when water is added: sand fills the gaps between stones, and cement fills the gaps between sand grains. Multiplying the finished volume by 1.54 gives the dry volume to buy.
The dry volume is then split by the ratio. For 1 : 2 : 3, there are six parts — one is cement, two are sand, three are gravel. A US bag of cement is 1 cu ft; metric bags are converted at 1,440 kg/m³.
Water is set by a water–cement ratio of 0.5 by weight — half a pound of water per pound of cement. Damp sand already carries water, so add it gradually.
Worked example
A 10 × 10 ft pad, 4 in thick, mixed at 1 : 2 : 3 with 10% extra.
- Wet volume: 10 × 10 × 0.333 = 33.3 cu ft; with 10% waste: 36.7 cu ft
- Dry volume: 36.7 × 1.54 = 56.5 cu ft
- Cement: 56.5 ÷ 6 = 9.4 cu ft → 10 × 94 lb bags
- Sand: 56.5 × 2 ÷ 6 = 18.8 cu ft = 0.70 cu yd ≈ 0.94 tons
- Gravel: 56.5 × 3 ÷ 6 = 28.2 cu ft = 1.05 cu yd ≈ 1.46 tons
- Water: 9.4 × 94 lb × 0.5 = 442 lb ≈ 53 gal
Buy 10 bags of Portland cement, about 0.94 tons of sand and 1.46 tons of gravel, and plan on roughly 53 gallons of water.
How much extra to allow
Some cement and aggregate is always lost to spills, the mixer drum and an uneven base.
| Situation | Allow |
|---|---|
| Formed pad on a level base | 5% |
| Typical site mixing | 10% |
Reading your result
The headline is the cement to buy. Sand and gravel are shown by volume and weight — suppliers sell by one or the other, so use whichever they quote.
If you end up needing more than about 1½ cubic yards, hand mixing becomes a long day. A ready-mix truck is usually cheaper at that point.
Assumptions
- Dry volume factor of 1.54, the usual site allowance (textbook values run 1.52–1.57).
- Sand weighs about 1.35 tons per cu yd and gravel about 1.4 tons per cu yd when loose. Wet material weighs more.
- Strength figures (about 3,000 psi for 1 : 2 : 3) assume clean aggregate, correct water and proper curing. Site mixes vary.
Unit conversions use exact definitions (1 in = 25.4 mm, 1 US gal = 3.785 L). See the calculation methodology for rounding rules.
When to call a professional
- Structural concrete — footings, foundations, beams — should use a specified mix, often ready-mix with a delivery ticket. Ask your engineer or building department.
Frequently asked questions
How many bags of cement in a cubic yard of concrete?
About 7 bags of 94 lb Portland cement for a 1 : 2 : 3 mix: 27 cu ft × 1.54 = 41.6 cu ft dry ÷ 6 parts = 6.9 cu ft of cement.
What is the best concrete mix ratio?
1 : 2 : 3 (cement : sand : gravel) is a reliable general-purpose mix for slabs and paths. Use 1 : 2 : 4 for mass footings and 1 : 1.5 : 3 where you need more strength.
Why multiply by 1.54?
Dry materials pack together when mixed with water, so the finished concrete takes up about two-thirds of the loose volume. 1.54 converts finished volume back to the dry material you need.
Is cement the same as concrete?
No. Cement is the binder; concrete is cement plus sand, gravel and water. For premixed bags, use the Concrete Bag Calculator instead.